If the start of the Interclub Spring Series is postponed due to the BYC gates remaining “in”, and blocking the exit of BYC boats from their harbour, then racing will start based on the following:

 

Gates Removed:

Impact on Racing:

Sunday:

Spring Series starts on Thursday.

Monday:

Spring Series starts on Thursday.

Tuesday:

Spring Series starts on Thursday.

Wednesday:

Any weekend race(s) will proceed and Spring Series starts the following Monday.

Thursday:

Any weekend race(s) will proceed and Spring Series starts the following Monday.

Friday:

No weekend or Monday night racing; Spring Series starts the following Tuesday.

Saturday:

No weekend or Monday night racing; Spring Series starts the following Tuesday.

Note that the BYC gates cannot be removed until the water level drops to roughly 59.0m ( or 1.1m above datum) — see this page for information on the Ottawa River water levels.

The above plan was agreed upon 2017-12-29 during a meeting between BYC and NSC Fleet Committee members.

Page updated: 2017-12-31.

Update log
2018:
23 May: DS: added (or 1.1m above dutum) to the note about gates.
2017:
30 Dec: HM: Page created, following agreement with BYC on this schedule, 2017-12-29.